Question: What is the slack time for activity E? Task Predecessor Duration Early Start Early Finish Late Start Late Finish A -- 8 B A 14

  1. What is the slack time for activity E?
    Task Predecessor Duration Early Start Early Finish Late Start Late Finish
    A -- 8
    B A 14
    C A 23 8
    D C, B 6 23 26
    E C 32
    F D, E 32 38

    0 days

    1 day

    4 days

    2 days