Question: What is the technical term for costs moving between one department and the next in a multi-department process? Multiple choice question. Prior costs Reduced costs
What is the technical term for costs moving between one department and the next in a multi-department process? Multiple choice question. Prior costs Reduced costs Transferred-in costs