Question: What is the WAPI for projects 1 & 2 combined. The total budget available is $146 PI Initial Cost Project 1 2.399 $43 Project 2


What is the WAPI for projects 1 & 2 combined. The total budget available is $146 PI Initial Cost Project 1 2.399 $43 Project 2 2.241 $17 What is the NPV of the following cashflow stream? The interest rate is 4.1%. Year [O]: $-81 Year 2: $51 Year 6: $83 Year 11: $47 What is the profitability index of a project with a NPV of $-425 and an initial cost of $126? (Answer in hundredths)