Question: What is time variance for activity A? Pick the best answer. A. 0.444 B. 0.167 C. 1.000 D. 0.250 E. 0.028 How long is the

What is time variance for activity A? Pick the

What is time variance for activity A? Pick the best answer.

A.

0.444

B.

0.167

C.

1.000

D.

0.250

E.

0.028

How long is the project expected to take? Pick the best answer.

A.

8.5 days

B.

7.5 days

C.

6.7 days

D.

10.7 days

E.

11.6 days

What is the variance for the expected project duration? Pick the best answer.

A.

2.528

B.

1.368

C.

2.083

D.

1.869

E.

1.586

What is the probability of completing the project within 8 days? Pick the best answer.

A.

0.03

B.

0.38

C.

0.97

D.

0.12

E.

0.88

What is the probability of completing the project in 11 days or more? Pick the best answer.

A.

0.41

B.

0.09

C.

0.32

D.

0.91

E.

0.59

What is the probability that the project completion time is between 9 and 12 days? Pick the best answer.

A.

0.82

B.

0.94

C.

0.45

D.

0.70

E.

0.62

Most Optimistic Pessimistic Activity Likely Activity Activity Predecessor Time Activity Time Time (days) (days) (days) A 1.5 2.0 5.5 B A 2.5 3.5 5.5 C A 0.4 0.5 0.6 D A 0.5 1.0 4.5 E B, C, D 1.0 3.0 F E 0.5 1.0 1.5 8.0 What is the expected activity time for activity D? Pick the best answer. O A. 1.0 day B. 1.5 days C. 4.0 days 1 D. 3.5 days O E. 4.6 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!