Question: What is time variance for activity A? Pick the best answer. A. 0.444 B. 0.167 C. 1.000 D. 0.250 E. 0.028 How long is the

What is time variance for activity A? Pick the best answer.
| A. | 0.444 | |
| B. | 0.167 | |
| C. | 1.000 | |
| D. | 0.250 | |
| E. | 0.028 |
How long is the project expected to take? Pick the best answer.
| A. | 8.5 days | |
| B. | 7.5 days | |
| C. | 6.7 days | |
| D. | 10.7 days | |
| E. | 11.6 days |
What is the variance for the expected project duration? Pick the best answer.
| A. | 2.528 | |
| B. | 1.368 | |
| C. | 2.083 | |
| D. | 1.869 | |
| E. | 1.586 |
What is the probability of completing the project within 8 days? Pick the best answer.
| A. | 0.03 | |
| B. | 0.38 | |
| C. | 0.97 | |
| D. | 0.12 | |
| E. | 0.88 |
What is the probability of completing the project in 11 days or more? Pick the best answer.
| A. | 0.41 | |
| B. | 0.09 | |
| C. | 0.32 | |
| D. | 0.91 | |
| E. | 0.59 |
What is the probability that the project completion time is between 9 and 12 days? Pick the best answer.
| A. | 0.82 | |
| B. | 0.94 | |
| C. | 0.45 | |
| D. | 0.70 | |
| E. | 0.62 |