Question: What might a project team do if the risk profile is lower during a re - evaluation in the implementation phase? Release contingency funds back
What might a project team do if the risk profile is lower during a reevaluation in the implementation phase?
Release contingency funds back to the parent organization.
Increase the contingency funds.
Stop the project immediately.
Start a new project with the excess funds.