Question: What must be done grouting new equipment? A ) Level and align machine coupling and attach at related fixtures B ) Level and align machine

What must be done grouting new equipment?
A)Level and align machine coupling and attach at related fixtures
B)Level and align machine base plate and attach at related fixtures
C)Level and align machine coupling and torque anchor bolts to of the torque
D)Level and align machine base plate and torque anchor bolt to of the torque