Question: What probability distribution method is used to estimate the expected time and its variances for activities of a project? O A Normal distribution B. Beta

What probability distribution method is used to

What probability distribution method is used to estimate the expected time and its variances for activities of a project? O A Normal distribution B. Beta distribution C. Exponential decay distribution D. Binomial distribution QUESTION 18 Which of the following statement is true for the critical path/ O A The path in the network with the longest duration OB. The path in a network with the shortest duration C. The path in the network with average duration D. The path with the least number of resources