Question: What risks could occur if the project manager decides to skip some of the ongoing monthly status meetings? ( check all that apply ) Missing

What risks could occur if the project manager decides to skip some of the ongoing monthly status meetings? (check all that apply)
Missing contractor help due to a recent labor shortge in the region.
Incorrect completion of tasks that require a "do over."
Cost impact of rising price increase of supplies, beyond the planned budget.
Any safety issues occuring on the job site.
Observe delays of completion of critical path tasks, possible impact on final completion date.
 What risks could occur if the project manager decides to skip