Question: What should a team do with a Product Backlog items they choose to bring into the Sprint? The team should break each product backlog item
What should a team do with a Product Backlog items they choose to bring into the Sprint?
The team should break each product backlog item into tasks and estimate each task in terms of effort.
The team asks the Scrum Master to research the product backlog items and decide who should work on each one.
The product owner assigns each product backlog item to the specialist best suited to carry out the work.
The team doesn't do anything with the product backlog items. Scrum doesn't use tasks or task lists.