Question: What should we NOT do to a workstep that is a bottleneck: Question 2 7 options: Develop ways to divert lower importance / non -

What should we NOT do to a workstep that is a bottleneck:
Question 27 options:
Develop ways to divert lower importance/non-critical units from the bottleneck to another lower cost work resource
Make sure that people or other resources constituting the bottleneck operation are treated and maintained well to ensure maximum availability
Increase bottleneck capacity by adding resources or finding improved work methods
Make sure it gets defect free units to work on
Offer incentives to the bottleneck resources to continue working at full capacity indefinitely