Question: What should your first reaction be if a customer asks for a change to your project scope baseline? Select one: a.Emphatically tell the customer no.
What should your first reaction be if a customer asks for a change to your project scope baseline? Select one: a.Emphatically tell the customer "no". b.Try to get the customer to accept the original project objectives without changing the scope. c.Call the team together and replan the project to accommodate the new scope. d.Document the scope changes and process them through the integrated change control system for approval