Question: What will happen to a project's schedule if an activity on the critical path is delayed due to limited resource availability? a . Nothing will

What will happen to a project's schedule if an activity on the critical path is delayed due to limited resource availability?
a. Nothing will happen to the project's schedule if an activity on the critical path is delayed.
b. The project's schedule will slip only if the float/slack period for the critical path activities is not enough to resolve the resource overload issue.
c. The project's schedule will slip only if the float/slack period for the noncritical activities is not enough to resolve the resource overload issue.
d. There is never a delay in the critical path, because it is the longest path through the network.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!