Question: What will happen to a project's schedule if an activity on the critical path is delayed due to limited resource availability? a . Nothing will
What will happen to a project's schedule if an activity on the critical path is delayed due to limited resource availability?
a Nothing will happen to the project's schedule if an activity on the critical path is delayed.
b The project's schedule will slip only if the floatslack period for the critical path activities is not enough to resolve the resource overload issue.
c The project's schedule will slip only if the floatslack period for the noncritical activities is not enough to resolve the resource overload issue.
d There is never a delay in the critical path, because it is the longest path through the network.