Question: When a contracting party refuses to complete the contract before the actual time of performance, it is called a ( n ) ante - breach
When a contracting party refuses to complete the contract before the actual time of performance, it is
called an
antebreach
executory renunciation
advance renunciation
anticipatory repudiation
preemptive strike