Question: When a project is completed on time, the project team must accomplish all of the following activities EXCEPT: Group of answer choices capture and share
When a project is completed on time, the project team must accomplish all of the following activities EXCEPT:
Group of answer choices
capture and share lessons learned.
plan a smooth transition of deliverables into ongoing operations.
secure customer feedback and approval.
use alternative dispute resolution.