Question: When a project is divided into phases, how do the Process Groups apply? a. It's usually not necessary to go through the Initiating Process Group
When a project is divided into phases, how do the Process Groups apply?
a.
It's usually not necessary to go through the Initiating Process Group again
b.
Planning of a prior phase will probably be sufficient for the next phase
c.
Monitoring and Controlling will be simplified because of your experience in a prior phase
d.
All Process Groups may be repeated for each phase
Change control procedures and reporting rules that All projects in the organization must follow are also known as what term?
a.
Governance framework
b.
Organizational process assets
c.
Policies
d.
Project charter
A project team views his PM as a member of management who can give them a good review and possibly give them a bonus. What type of power does this project manager have?
a.
Punitive
b.
Situational
c.
Reward
d.
Guilt-based