Question: When a project is finished after day 2 0 , a penalty cost of $ 1 0 0 per day will be incurred for every

When a project is finished after day 20, a penalty cost of $100 per day will be incurred for every day the project is delayed beyond day 20. An indirect cost $50 per day is incurred every day. According to the maximum profit plan, what is the bonus if we crash the project duration from 22 days to 21 days: