Question: When a project manager arrives mid-way through a project and needs to rebuild the plan and team momentum, which project schedule information should inform
"When a project manager arrives mid-way through a project and needs to rebuild the plan and team momentum, which project schedule information should inform new task estimates?" A. Actual performance data from within the project. B. Work breakdown structure C. Total float per task D. Early Start and Late Start per task
Step by Step Solution
There are 3 Steps involved in it
In the scenario where a project manager joins a project midway and aims to reconstruct the plan and ... View full answer