Question: When a Project Manager uses the crashing or fast tracking schedule compression technique, it is very important they consider which of the following: ( select

When a Project Manager uses the crashing or fast tracking schedule compression technique, it is very important they consider which of the following: (select the best possible answer). A. Crashing and fast tracking are schedule compression techniques that can create both opportunities and threats to the schedule.
B. Crashing might add resources at additional cost to the project, but might not accomplish the desired result.
C. Fast tracking might add time to the schedule due to the need for rework.
D. All of the above.