Question: When a project undergoes drastic scope changes and requires resetting the budget, it is called: a. Budget reallocation b. Variance analysis c. Cost baseline update
When a project undergoes drastic scope changes and requires resetting the budget, it is called: a. Budget reallocation b. Variance analysis c. Cost baseline update d. Rebaselining