Question: When a project's critical path is longer than the allotted schedule, this is referred to as: A ) having negative float B ) a cost
When a project's critical path is longer than the allotted schedule, this is referred to as:
A having negative float
B a costschedulequality equilibrium
C having slack
D none of the above