Question: When a project's critical path is longer than the allotted schedule, this is referred to as: A ) having negative float B ) a cost

When a project's critical path is longer than the allotted schedule, this is referred to as:
A) having negative float
B) a cost-schedule-quality equilibrium
C) having slack
D) none of the above