Question: When a risk with a high probability or high impact to the project is identified, extra time should be calculated into the activity to compensate.
When a risk with a high probability or high impact to the project is identified, extra time should be calculated into the activity to compensate. This is called: Group of answer choices optimistic estimating pessimistic estimating three-point estimating contingency estimating