When an activities late start is earlier than it's early start, the activity
Hide Transcribed Text
an an activity's late start is earlier than its early start, the activity Has negative float May have a lead applied Is on the critical path Has positive float You are in the process of estimating an activity and have received the followi However, the team says it usually takes14.5days. What is the PERT estimate14.23days