Question: When analyzing project performance using EVA, what does the term 'Planned Value' ( PV ) refer to ? Option A The actual cost spent on
When analyzing project performance using EVA, what does the term 'Planned Value' PV refer to
Option A
The actual cost spent on completed work
Option B
The anticipated final deliverable value
Option C
The total budget for the project
Option D
The value of the work that was planned to be completed by a specific time.