Question: When are contracts using simplified acquisition procedures considered closed? Six months after physical completion of the contract When the contracting officer receives evidence of receipt
When are contracts using simplified acquisition procedures considered closed? Six months after physical completion of the contract When the contracting officer receives evidence of receipt of supplies pr service and receipt of final payment Within 36 months of evidence of physical completion Within 36 months of physical completion
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts