Question: When are indents used in Ms - Project task lists? a ) To represent WBS Hierarchy of activities. b ) To indicate tasks that occur
When are indents used in MsProject task lists?
a To represent WBS Hierarchy of activities.
b To indicate tasks that occur after other tasks.
c To identify Miletone events
d To indicate tasks with estimated deliveries that will be completed later.