Question: When are indents used in Ms - Project task lists? a ) To represent WBS Hierarchy of activities. b ) To indicate tasks that occur

When are indents used in Ms-Project task lists?
a) To represent WBS Hierarchy of activities.
b) To indicate tasks that occur after other tasks.
c) To identify Miletone events
d) To indicate tasks with estimated deliveries that will be completed later.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!