Question: When award without discussions is not stated in the solicitation and the selection process is not a lowest price technically acceptable, the Contracting Officer will
When award without discussions is not stated in the solicitation and the selection process is not a lowest price technically acceptable, the Contracting Officer will
| Cancel the solicitation and reissue. | ||
| Establish a competitive range consisting of the most highly rated proposals. | ||
| Allow discussions anyway. | ||
| Start negotiations without establishing a competitive range. |
Developing the evaluation criteria and factors is an activity completed in the Planning Phase. The evaluation criteria and ratings
| Help industry understand where to focus their resources while building the proposals. | ||
| Assist the Source Selection Authority in making trade-off analysis between offerors. | ||
| Must provide a meaningful distinction between offers. | ||
| All of these are correct. |
When performing on a Source Selection Board, the members will
| Evaluate all proposals against each of the other proposals. | ||
| Evaluate all the proposals together as a group. | ||
| Evaluate all proposals independently of other proposals. | ||
| Only evaluate the most appeasing proposals. |