Question: When breaking down tasks, a guideline for breaking a task down further is Question 21 options: A) It will make task responsibility and accountability more

When breaking down tasks, a guideline for breaking a task down further is

Question 21 options:

A)

It will make task responsibility and accountability more clear.

B)

The smaller tasks will be easier to estimate.

C)

All answers are correct.

D)

The smaller tasks will be easier to track for cost and schedule progress.

Question 22 (1 point)

ListenReadSpeaker webReader: Listen

In order to win a new contract the project recruited another firm with complementary strengths to improve their probability of success. Both firms will participate in rewards of the contract. This is an example of what type of opportunity response?

Question 22 options:

A)

Share

B)

Exploit

C)

Enhance

D)

Accept

Question 23 (1 point)

ListenReadSpeaker webReader: Listen

Which of the following is true about a phased estimate?

Question 23 options:

A)

The scope may increase, decrease, or stay the same at a phase gate.

B)

It reduces risk for the project's owner and the project team.

C)

It is assumed that some projects will be cancelled at a phase gate review.

D)

All answers are correct.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!