Question: When calculating total project costs, do you add or subtract incentives? For example, crashing a project by one day will produce a total direct cost
When calculating total project costs, do you add or subtract incentives? For example, crashing a project by one day will produce a total direct cost of $9800 but an incentive of $500. What is the total project cost?