Question: When choosing tasks to crash in the project schedule, it is important to consider all of these except __________ a. if the task is on

When choosing tasks to crash in the project schedule, it is important to consider all of these except __________ a. if the task is on the critical path b. inherent risk in the task c. timing of the task in the network d. if the task is a Burst activity e. The Crash Slope