Question: When closing a project or a project phase, which document should the project manager refer to for information on the status of change requests throughout

When closing a project or a project phase, which document should the project manager refer to for information on the status of change requests throughout the tenure of the project/phase?A) Project communicationsB) Assumption logC) Issue logD) Change log