Question: When comparing processes for a crossover chart, which of the following is not true? a. A calculated indifference point might not be included in the
When comparing processes for a crossover chart, which of the following is not true?
a. A calculated indifference point might not be included in the summary of best processes.
b. The process with the lowest fixed costs will be best for lowest volumes
c. The process represented by the line with the steepest slope will be best for highest volumes
d. Quality is not a consideration; only total costs.
e. The process with the lowest variable costs will be best for highest volumes.