Question: When conducting a stakeholder analysis, what does influence measure? 1 point How much the stakeholder s actions affect the project outcome How many meetings the
When conducting a stakeholder analysis, what does influence measure?
point
How much the stakeholders actions affect the project outcome
How many meetings the stakeholder participates in
How many tasks the stakeholder is able to assign
How much interest the stakeholder has in the project