Question: When considering Mr . Iam's project above, what might be some possible high - level milestones? A . Project team assembled B . Charter written

When considering Mr. Iam's project above, what might be some possible high-level milestones?
A.
Project team assembled
B.
Charter written and signed off
C.
One assembly line converted to begin producing new widgets
D.
High-level cost estimates provided