Question: When controlling a project, how is up-to-date information about resources, costs, quality, and budgets used? Part 2 A. to learn project shortcomings before they are
When controlling a project, how is up-to-date information about resources, costs, quality, and budgets used?
Part 2
A.
to learn project shortcomings before they are detected by higher management
B.
to shift resources to where they are needed most
C.
to determine who needs to be reminded of the project plan
D.
to be able to plot graphs for the final project report