Question: When crashing a project, our first task is to develop what?a ) A table or graph of the cost of a project as a function
When crashing a project, our first task is to develop what?a A table or graph of the cost of a project as a function of the project's possible completion datesb A schedule that shows the risks associated with each activity in the projectc A list that shows the activities and the events of a project without referring to the costsd A table showing the noncritical activities and the cost associated with each of those activities