Question: When crashing a project, the first activity your crash should be Multiple choice question. the one with the lowest crash cost per day. the one
When crashing a project, the first activity your crash should be Multiple choice question. the one with the lowest crash cost per day. the one with the highest crash cost per day. on the critical path with the lowest crash cost per day. on the critical path with the highest crash cost per day