Question: When developing a project budget, it is useful to refer to the project schedule. What information does the project schedule provide? a. Effort estimates for
When developing a project budget, it is useful to refer to the project schedule. What information does the project schedule provide? a. Effort estimates for completing deliverables b.Documentation of the costs related to similar deliverables c.A helpful reminder of planned project outcomes d.A list of identified requirements for deliverables