Question: When do the sponsor and customer representatives first provide feedback on deliverables in an adaptive project? When deliverable iteration is completed When the deliverables are
When do the sponsor and customer representatives first provide feedback on deliverables in an adaptive project?
When deliverable iteration is completed
When the deliverables are completed
When the deliverables review is completed
When the project with deliverables is completed