Question: When estimating resources for activities to estimate the activity's duration, the a . availability of each resource has to be taken into account b .
When estimating resources for activities to estimate the activity's duration, the
a availability of each resource has to be taken into
account
b name of each resource has to be taken into
c cost of each resource has to be taken into account.
account.
d security clearance of each resource has to be taken into account: