Question: When forecasting the final project cost, the method called EAC f (Forecasted Total Cost at Completion) is used when ____________ A. the original budget is
When forecasting the final project cost, the method called EACf (Forecasted Total Cost at Completion) is used when ____________
A. the original budget is unreliable.
B. the original budget has a +/- factor of not more than 10%.
C. the original budget is reliable.
Which of the following is not an identified objective in scheduling?
A. Maximize work in process inventory
B. Minimize time in the system
C.Meet consumer due dates