Question: When implementing a business continuity plan, an organization reaches a predetermined state, known as a ( n ) at when the responsible executive indicates that
When implementing a business continuity plan, an organization reaches a predetermined state, known as an at when the responsible executive indicates that the organization will relocate to a preselected alternate site.
a contingency point
b moving point
c trigger point
d critical point