Question: When in a hurry to complete a project where time is of the essence, and rework is possible, which method of reducing project duration is
When in a hurry to complete a project where time is of the essence, and rework is possible, which method of reducing project duration is most appropriate?
Multiple choice question.
Improve the efficiency of the project team
Do it twicefast and correctly
Add resources to the project
Schedule overtime