Question: When is passive risk acceptance an appropriate approach? A . When the likeliness of risk occurrence is very low. B . When the risk occurrence
When is passive risk acceptance an appropriate approach?
A When the likeliness of risk occurrence is very low.
B When the risk occurrence is hard to identify.
C When it is best to deal with a risk as it occurs.
D When the risk cannot be assessed or analyzed.