Question: When managing a small construction project, the project manager has informed the project team members that they are using too many materials to complete the
When managing a small construction project, the project manager has informed the project team members that they are using too many materials to complete the project work. The project manager feels the team members could utilize a lot less materials to accomplish the work they're currently doing. What process describes this scenario? A develop team B control resources C. monitor resources D, Manage team