Question: When material is ordered from a vendor, which of the following is not a reason for delays in the order arriving on time? Question 1

When material is ordered from a vendor, which of the following is not a reason for delays in the order arriving on time?
Question 18 options:
An unexpected strike at the vendor's plant
A shortage of material at the vendor's plant causing backlogs
Normal variation in shipping time
Redundant ordering systems