Question: When multiple Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint? ( choose the best answer )
When multiple Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint?
choose the best answer
A Yes, but only for Scrum Teams whose work has dependencies.
B No that is far too hard and must be done in a hardening Sprint.
C Yes, in order to accurately inspect what is done.
D No each Scrum Team stands alone.