Question: When performing a forward pass calculation to determine the early dates in a CPM schedule, the calculation of an early start of an activity is
When performing a forward pass calculation to determine the early dates in a CPM schedule, the calculation of an early start of an activity is based on the latest timing created by the logic flow options from all predecessors, considering the effect of any lags that may apply.