Question: When planning for how test and evaluation will be conducted, which document provides the project manager with high-level information about the criteria you are testing

When planning for how test and evaluation will be conducted, which document provides the project manager with high-level information about the criteria you are testing for? O Change Management Plan O Quality Management Plan O Test and Evaluation Plan O Risk Management Plan