Question: When preparing the WBS , what level of breakdown is advisable? a . The level at which the work package can be monitored and controlled

When preparing the WBS, what level of breakdown is advisable?
a.
The level at which the work package can be monitored and controlled
b.
A level at which it is impossible to break it down further
c.
The level preferred by the project manager
d.
The level of concrete activities