Question: When project managers use the WBS to estimate the project resources, it means that they are using _ _ _ _ _ _ _ _

When project managers use the WBS to estimate the project resources, it means that they are using ______________.
A.
Alternative analysis
B.
Bottom-up estimating
C.
Analogous estimating
D.
Expert judgment