Question: When project managers use the WBS to estimate the project resources, it means that they are using _ _ _ _ _ _ _ _
When project managers use the WBS to estimate the project resources, it means that they are using
A
Alternative analysis
B
Bottomup estimating
C
Analogous estimating
D
Expert judgment